The Price of Uncertainty: Who Pays When Scale-Up Goes Wrong?

How fixed-price, cost-plus, and hybrid CDMO contracts change the economics of scientific risk.
Bench to Strategy | Financial Strategy Case
A pharmaceutical manufacturing process that works at laboratory scale may behave differently when scaled for clinical production. Changes in heat transfer, mixing, and crystallization can introduce unexpected challenges, requiring additional experiments to maintain product quality, improve yield, or establish a reproducible process.
The FDA's ICH Q11 guidance emphasizes the importance of understanding manufacturing processes and establishing appropriate controls.
For a biotech sponsor outsourcing development to a contract development and manufacturing organization (CDMO), this scientific uncertainty creates a financial question:
Who pays when the process requires more development than anticipated?
The answer often depends on the contract signed before the work began.
Understanding the Contract Structures
Pharmaceutical development and manufacturing agreements can incorporate numerous pricing and risk-sharing provisions. For this analysis, we focus on fixed-price and cost-plus contracting, alongside a simplified hybrid arrangement. These illustrative structures demonstrate how financial exposure can shift between sponsors and CDMOs.
Fixed-price contracting
Under a fixed-price agreement, the sponsor pays a predetermined amount for a defined scope of work. The CDMO generally absorbs the cost of unexpected in-scope work, while retaining additional profit if actual costs are lower than anticipated.
The sponsor gains price predictability, but the CDMO may include a contingency premium to compensate for accepting financial risk. Fixed service pricing appears in publicly filed CDMO agreements. For example, the Lonza–Cabaletta Bio agreement establishes service pricing while allowing certain materials and additional services to be charged separately.
Cost-plus contracting
Under cost-plus, the sponsor reimburses eligible project costs plus an agreed fee or markup. For example, $800,000 in eligible costs with a 25% markup results in a $1 million payment. If costs rise to $1 million, payment increases to $1.25 million, assuming the expenses are authorized and reimbursable.
This structure provides flexibility but transfers more cost variability to the sponsor. However, cost-plus does not necessarily mean unlimited spending. Agreements may establish approved budgets, spending ceilings, and procedures requiring authorization before costs exceed those limits. Fee structures may also vary.
Cost-plus pricing is used in pharmaceutical manufacturing. MannKind Corporation's 2023 SEC Form 10-K identifies its commercial supply agreement with United Therapeutics for Tyvaso DPI as a cost-plus arrangement.
Hybrid contracting
Hybrid agreements combine fixed pricing with variable reimbursement. A sponsor might pay a defined base price while separately funding approved additional development work, subject to a negotiated ceiling.
The CDMO may charge a higher initial price in exchange for assuming financial responsibility once that ceiling is reached.
The distinction is not whether scientific uncertainty exists, but how its financial consequences are allocated.
A Fictional CDMO Scale-Up Case
Meridian Therapeutics, a fictional biotech company developing a small-molecule oncology treatment, has successfully produced 500-gram laboratory batches.
To support clinical development, Meridian engages Apex Pharma Manufacturing, a fictional CDMO, to optimize the synthesis process and manufacture a 20-kilogram batch of active pharmaceutical ingredient (API).
Apex estimates internal project costs of $800,000, including development, materials, manufacturing, analytical testing, and allocated overhead. However, changes in crystallization behavior during scale-up could require additional work.
Meridian evaluates three proposals:
Contract | Proposed terms |
Fixed price | $1.2 million for the agreed scope |
Cost-plus | Eligible actual costs plus 25% markup |
Hybrid | $1.1 million base plus approved incremental costs above $800,000, reimbursed without markup, capped at $200,000 additional |
Under the hybrid, Meridian's maximum modeled payment is $1.3 million. Apex absorbs further in-scope costs unless the agreement is amended.
All three proposals cover the same intended deliverables. For comparison, the model assumes eligible costs, unchanged scope, and any necessary approvals. Cost-plus is modeled without a spending ceiling to isolate its pricing mechanics, although actual agreements may impose one.
Three Contracts, One Scientific Problem
During scale-up, Apex discovers that crystallization produces an unacceptable particle-size distribution. Additional experiments, process modifications, and analytical testing increase actual costs to $950,000.
The resulting financial outcomes are:
Financial measure | Fixed price | Cost-plus | Hybrid |
Actual CDMO cost | $950,000 | $950,000 | $950,000 |
Sponsor payment | $1,200,000 | $1,187,500 | $1,250,000 |
CDMO project profit | $250,000 | $237,500 | $300,000 |
Under fixed price, Apex absorbs the additional costs without changing Meridian's payment. Cost-plus passes the eligible expenses and markup to Meridian. Hybrid reimburses the approved $150,000 overrun without markup, in addition to its higher base price.
Cost-plus is the least expensive option for Meridian in this scenario. But the result changes if scale-up proceeds without complications—or becomes substantially more expensive.
Exhibit 1: The Cost of Transferring Scale-Up Risk
Total sponsor payment as actual CDMO project costs increase.

Fixed-price payments remain constant, cost-plus payments rise with eligible expenses, and hybrid payments increase until the $1.3 million ceiling is reached.
The graph reveals the trade-off: lower initial payments offer savings when development proceeds smoothly, while greater price protection becomes valuable as costs increase.
The Hidden Cost of Financial Certainty
A CDMO accepting financial risk must consider the likelihood and magnitude of unexpected work. That assessment may be reflected in its quote.
In Meridian's case, the $1.2 million fixed-price agreement costs $200,000 more than the $1 million baseline cost-plus payment and $100,000 more than the hybrid base price.
If scale-up proceeds without complications, Meridian pays that additional amount despite requiring no extra development.
But if actual costs reach $1.2 million, the outcomes reverse:
Contract | Sponsor payment |
Fixed price | $1,200,000 |
Hybrid | $1,300,000 |
Cost-plus | $1,500,000 |
Fixed price now saves Meridian $300,000 compared with cost-plus and $100,000 compared with hybrid.
The sponsor has paid for protection against an unfavorable outcome. Whether that protection is worthwhile depends on how likely the outcome is.
Where Does the Financial Advantage Change?
For fixed-price and cost-plus, the break-even point is:
Break-even actual cost = Fixed price ÷ (1 + markup)
$1,200,000 ÷ 1.25 = $960,000
Below $960,000 in eligible actual costs, cost-plus is less expensive than fixed price. Above that threshold, fixed price becomes less expensive.
This calculation compares only those two agreements and does not account for administrative expenses or contractual spending limits.
To evaluate all three proposals before costs are known, Meridian must also consider the probability of complications.
Exhibit 2: Expected Sponsor Payment by Complication Probability
Suppose Meridian models two possible outcomes:
Normal scale-up: $800,000 in actual CDMO costs.
Significant complications: $1.2 million in actual CDMO costs.
The expected sponsor payment is the probability-weighted average of those outcomes.
Probability of complications | Fixed price | Cost-plus | Hybrid | Lowest expected payment |
0% | $1.200M | $1.000M | $1.100M | Cost-plus |
10% | $1.200M | $1.050M | $1.120M | Cost-plus |
25% | $1.200M | $1.125M | $1.150M | Cost-plus |
33.3% | $1.200M | $1.167M | $1.167M | Cost-plus / Hybrid |
40% | $1.200M | $1.200M | $1.180M | Hybrid |
50% | $1.200M | $1.250M | $1.200M | Hybrid / Fixed |
75% | $1.200M | $1.375M | $1.250M | Fixed price |
100% | $1.200M | $1.500M | $1.300M | Fixed price |
Exhibit 2. Expected sponsor payments under hypothetical complication probabilities. Values are rounded and do not represent observed manufacturing failure rates.
The preferred agreement changes as Meridian's assessment of risk increases:
Below approximately 33.3%: Cost-plus provides the lowest expected payment.
Between approximately 33.3% and 50%: Hybrid becomes the least expensive.
Above 50%: Fixed price provides the lowest expected payment.
At the boundaries, the relevant agreements have equal expected payments. These thresholds reflect the fictional pricing terms and assumed cost outcomes—not general industry benchmarks.
More importantly, the lowest expected payment is not necessarily the lowest-risk decision.
How Much Should a Sponsor Pay to Transfer Risk?
A sponsor must evaluate both expected expenditure and its ability to absorb an unfavorable outcome. A well-funded biotech company managing several programs may accept variable costs to avoid paying a substantial upfront risk premium. An early-stage company with limited cash runway may place greater value on predictability.
For the latter, an unexpected $300,000 expenditure could delay a clinical milestone, consume capital intended for another program, or create additional financing needs.
Hybrid contracting offers a middle ground: a higher starting price in exchange for a negotiated limit on additional reimbursement. But financial protection depends on the agreement's actual provisions. Scope exclusions, change orders, pass-through expenses, and approval procedures can materially affect the final payment.
The Cost of Managing Financial Uncertainty
Contract structure also influences administrative costs.
Because cost-plus reimbursement depends on recorded eligible expenses, effective implementation generally requires reliable cost accounting, supporting documentation, financial reporting, and expense approval controls. Sponsors may negotiate audit rights and procedures for approving budget increases. These safeguards provide transparency and spending discipline, but they can increase administrative work for both parties.
Fixed-price agreements also require oversight, particularly of scope changes, deliverable acceptance, and change orders.
The lowest expected contract payment may not represent the lowest total cost once financial oversight and contract management are considered.
Before signing, a sponsor should ask:
How likely is additional development, and how costly could it become?
What premium is being charged to transfer financial risk?
How much unexpected spending can the development program absorb?
What costs qualify for reimbursement, and who approves budget increases?
What protections remain when spending limits are reached or scope changes?
The publicly filed Lonza–Cabaletta Bio agreement illustrates why these distinctions matter: firm prices for defined services can coexist with separately charged materials and provisions addressing changes in scope. Ultimately, financial exposure is determined by the negotiated contract provisions—not simply the pricing label.
Certainty Has a Price. So Does Uncertainty.
Outsourcing decisions are often framed around technical capabilities, timelines, and quoted costs. Yet contract structure also determines how the financial consequences of scientific uncertainty are shared.
Fixed-price agreements offer predictability, potentially at a premium. Cost-plus offers flexibility but greater cost variability within negotiated controls. Hybrid arrangements distribute exposure through a combination of upfront pricing and reimbursement limits. The appropriate choice depends on process maturity, the probability and cost of additional development, administrative requirements, and the sponsor's financial capacity.
Choosing a contract is not deciding whether to pay for scientific uncertainty. It is deciding how much to pay for protection against its consequences.
Before signing a CDMO agreement, the more important question may not be simply What will this project cost?
It is What are we paying to transfer the risk—and is that protection worth its price?
References
U.S. Food and Drug Administration. (2012). Q11 Development and Manufacture of Drug Substances. Guidance for Industry.
U.S. Food and Drug Administration. (2011). Process Validation: General Principles and Practices. Guidance for Industry.
Lonza Houston Inc. and Cabaletta Bio, Inc. (2024). Development and Manufacturing Services Agreement. SEC Exhibit 10.1.
MannKind Corporation. (2024). Annual Report on Form 10-K for the fiscal year ended December 31, 2023. U.S. Securities and Exchange Commission.
Editor's note: Meridian Therapeutics and Apex Pharma Manufacturing are fictional. All pricing, probabilities, project costs, and outcomes are illustrative rather than industry benchmarks. The model assumes unchanged scope, eligible costs, and required approvals. It excludes financing, delays, and administrative expenses from the numerical comparisons. Actual agreements may establish spending caps and additional controls.